Skip to main content

Project

Excel Phase 3,
London Dockside

DJI 20230723085731 0018 V

Severfield was appointed to the ExCeL Phase 3 project, which involved the expansion of the venue to the east. This expansion added an impressive 25,000sqm to the existing space, bringing the total area to 125,000sqm upon completion.

Location
London Dockside
Client
AESC
Main Contractor
McLaren Construction
Engineer
Campbell Reith
Architect
Grimshaw Global
Tonnage
4,500

We provided approximately 4,500 tonnes of steelwork, including the construction of long-spanning mezzanine and roof trusses that span the full width of the building, providing large internal areas for future exhibitions.

We were also entrusted with supplying various components such as metal decking, cold rolled purlins, stairs, and intumescent paint on the project. Each of these elements played a crucial role in the overall functionality of the structure.

DJI 20230723085508 0002 V

One of the most challenging aspects of the project was ensuring that our work did not disrupt the ongoing operations of the existing ExCeL Phase 1 and 2 buildings. From the outset, we faced pressure to meet tight deadlines, particularly with the request to complete half of the main steelwork to provide a stable structure for the annual Formula E Event.

Despite the challenges posed by the project’s scale, we successfully completed the project scope within the required timeframes.